A two stage negotiated project constructed over 18 months where ABL was selected as the main contractor prior to design being finalised.

Our client benefitted from early contractor engagement where ABLs expertise was utilised at the design and elemental pricing stage and assisted to bring the project in “on time and under budget” by utilising the most cost effective building methods and most suitable contractors for the project.

A good mix of businesses now occupy the 22 unit combined office and warehouse development.

JOB SPECIFICATION

Contract Value: $10m
Contract Period: 18 months
Client: Stark Drive Limited Partnership
Architect: DD Architects Ltd
Structural Engineers: Powell Fenwick Consultants Ltd
Quantity Surveyor: Rider Levett Bucknall

REFEREE: Lindsey Topp 021 368 146