Queenstown - Wakatipu High School Gym and Robertson Block Extension

The project comprised 2 separate parts. The construction of 2 new classrooms and 2 new changing rooms and refurbishment of existing and the creation of a new Performing Arts & Music Centre as an extension to the existing Robertson Block.

The Performing Arts and Music Centre contains an acoustic rated music theatre and a drama theatre as well as four rehearsal rooms, a band room, a lecture room, grand entrance way and ancillary spaces.

The completed Performing Arts & Music Centre is a valued asset to the school and wider community.

Job Specification

  • Contract Value: $2.2m
  • Contract Period: 9 months
  • Client: Wakatipu High School Board of Trustees
  • Project Manager: Octa Associates
  • Architects: NZCAD
  • Structural Engineer: Gridline

Referees

  • Steve Henderson: NZCAD - 03 442 4195