The project consisted of the transformation of an old warehouse into a fully functioning brewery.

The project was complete in 20 weeks and consisted of the demolition & rebuild of the brewery floor slab & a front façade.

The internal fit out included an off licence area, offices, meeting room & a mezzanine viewing platform overlooking the brewery.

Want to know more about this project? Feel free to contact:

  • Darren Wright: 021 511 325 (Wright Consulting) Client Representative
  • Andrew Smithson: 03 356 3376 (DD Architects)
  • Ralph Bungard: 021 615 688 (Three Boys Brewery)

Project Details

Contract Value
$637K
Contract Period
20 Weeks